Project financials
The Finance tab on every project tracks budget, actuals, forecast and EVM.
Budget structure
- Approved budget — the £ amount signed off
- Contract value — what you'll bill the customer (may differ from budget)
- Forecast — current best estimate of total cost at completion (EAC)
- Actuals — what you've actually spent so far
These four numbers should reconcile. Sageon Business flags variances.
Financial tasks (line items)
Add cost lines via Finance → Financial tasks → + New line:
- Description (e.g. "Senior dev × 4 weeks")
- Type — Labour / Materials / Subcontractor / Other
- Budget £
- Actual £ (update as invoices come in)
- Period — month/quarter
Sageon rolls these up automatically.
EVM (Earned Value Management)
Once you have milestones with £ values and actuals against them, Sageon computes:
- PV (Planned Value) — what should be done by now
- EV (Earned Value) — what's actually been delivered
- AC (Actual Cost) — what's been spent
- CPI = EV / AC — cost efficiency
- SPI = EV / PV — schedule efficiency
- EAC — forecast cost at completion
See PMO acronyms for full definitions.
Reading the EVM dashboard
- CPI < 0.9 → over budget for work delivered → escalate
- SPI < 0.9 → behind schedule → re-plan
- Both > 1.0 → ahead and under → great, but check assumptions
Forecasting (EAC)
EAC is recalculated whenever actuals change. The simple formula Sageon uses: EAC = Budget × (1/CPI).
Or ask Sage
"Why is CPI dropping on Customer Portal?"
Sage will read the financial data and explain.
Tips
- Update actuals at least monthly. Stale actuals = useless EVM.
- Don't game EV by inflating milestone values. Milestones should reflect customer-perceived value, not internal effort.