Project financials

The Finance tab on every project tracks budget, actuals, forecast and EVM.

Budget structure

  • Approved budget — the £ amount signed off
  • Contract value — what you'll bill the customer (may differ from budget)
  • Forecast — current best estimate of total cost at completion (EAC)
  • Actuals — what you've actually spent so far

These four numbers should reconcile. Sageon Business flags variances.

Financial tasks (line items)

Add cost lines via Finance → Financial tasks → + New line:

  • Description (e.g. "Senior dev × 4 weeks")
  • Type — Labour / Materials / Subcontractor / Other
  • Budget £
  • Actual £ (update as invoices come in)
  • Period — month/quarter

Sageon rolls these up automatically.

EVM (Earned Value Management)

Once you have milestones with £ values and actuals against them, Sageon computes:

  • PV (Planned Value) — what should be done by now
  • EV (Earned Value) — what's actually been delivered
  • AC (Actual Cost) — what's been spent
  • CPI = EV / AC — cost efficiency
  • SPI = EV / PV — schedule efficiency
  • EAC — forecast cost at completion

See PMO acronyms for full definitions.

Reading the EVM dashboard

  • CPI < 0.9 → over budget for work delivered → escalate
  • SPI < 0.9 → behind schedule → re-plan
  • Both > 1.0 → ahead and under → great, but check assumptions

Forecasting (EAC)

EAC is recalculated whenever actuals change. The simple formula Sageon uses: EAC = Budget × (1/CPI).

Or ask Sage

"Why is CPI dropping on Customer Portal?"

Sage will read the financial data and explain.

Tips

  • Update actuals at least monthly. Stale actuals = useless EVM.
  • Don't game EV by inflating milestone values. Milestones should reflect customer-perceived value, not internal effort.