Project Management Plan (PMP)
The PMP is the formal, comprehensive plan that governs how a project is run. Sageon Business gives you a 17-section template aligned to PMBOK / PRINCE2 best practice.
When to write a PMP
- For any project above £100k or 6 months
- For all government / regulated work where it's mandated
- When the project crosses multiple programmes or organisations
For small internal projects, a PIM alone is enough.
The 17 sections
- Project Overview (business case, alignment, objectives, success criteria, benefits)
- Scope (in/out of scope, deliverables, exclusions)
- Approach & Methodology
- Schedule (milestones, dependencies, critical path)
- Cost & Budget
- Resource Plan
- Governance
- Risk Management approach
- Issue & Change Management approach
- Quality Management
- Communications Plan
- Procurement
- HSE & Compliance
- Benefits Realisation
- Closure approach
- Appendices & References
- Sign-off
How sections flow
Sageon Business pulls some fields from the PIM, RAID, milestones and stakeholders — so you're not retyping. Other sections are free-text.
Each section can be:
- Drafted
- Reviewed (by the PM)
- Approved (by the sponsor)
Progress tracking
A progress strip at the top shows X/17 sections complete. The PMP can be exported as PDF for sign-off.
Updating after kickoff
The PMP is a living document. Update relevant sections:
- After every change request
- At each gate / phase boundary
- When risks or scope materially change
Tips
- Don't write the whole PMP in one go. Bring sections to steering meetings for review one at a time.
- The Comms Plan and Governance sections are the most-used post-kickoff. Make sure those are precise.
- Sign-off matters. An unsigned PMP is a draft. Get the sponsor approval recorded.