Project Management Plan (PMP)

The PMP is the formal, comprehensive plan that governs how a project is run. Sageon Business gives you a 17-section template aligned to PMBOK / PRINCE2 best practice.

When to write a PMP

  • For any project above £100k or 6 months
  • For all government / regulated work where it's mandated
  • When the project crosses multiple programmes or organisations

For small internal projects, a PIM alone is enough.

The 17 sections

  1. Project Overview (business case, alignment, objectives, success criteria, benefits)
  2. Scope (in/out of scope, deliverables, exclusions)
  3. Approach & Methodology
  4. Schedule (milestones, dependencies, critical path)
  5. Cost & Budget
  6. Resource Plan
  7. Governance
  8. Risk Management approach
  9. Issue & Change Management approach
  10. Quality Management
  11. Communications Plan
  12. Procurement
  13. HSE & Compliance
  14. Benefits Realisation
  15. Closure approach
  16. Appendices & References
  17. Sign-off

How sections flow

Sageon Business pulls some fields from the PIM, RAID, milestones and stakeholders — so you're not retyping. Other sections are free-text.

Each section can be:

  • Drafted
  • Reviewed (by the PM)
  • Approved (by the sponsor)

Progress tracking

A progress strip at the top shows X/17 sections complete. The PMP can be exported as PDF for sign-off.

Updating after kickoff

The PMP is a living document. Update relevant sections:

  • After every change request
  • At each gate / phase boundary
  • When risks or scope materially change

Tips

  • Don't write the whole PMP in one go. Bring sections to steering meetings for review one at a time.
  • The Comms Plan and Governance sections are the most-used post-kickoff. Make sure those are precise.
  • Sign-off matters. An unsigned PMP is a draft. Get the sponsor approval recorded.